The following are pictures that I've received from one of the residents of their completed project - Daadys Olive. Apparently  the Olive residents made number of followups during the past one year with the builder to do the finishing touches and are now fedup with the builder and gave up.  The following is a letter to builder by their residents one year back.




Shot at Location on 12 May 2012 - Incomplete Grill/Wall Painting @Daadys Olive Basement

Shot at location on 12 May 2012, Incomplete Painting and  the promised letter box (1 letter box for all 32 flats :) )

Shot at location on 12 May 2012, Incomplete Painting (pillars to be painted YELLOW). Substandard paintiing/marking of parking lots. 


Water seepage through walls in Basement from Drainage adjacent to the project



Some more pictures that I've taken in the layout recently...


The Swimming Pool...As on 01 July 2012

Jogging Track and Park..This used to be beautiful  park with jogging track some 3 years back but got completely damaged due to clubhouse/swimming pool construction and water seepage from adjacent lake


Club House/Gym as on 01 July 2012